Project timeline terms worth agreeing on
A project timeline is a dated plan of every phase from kickoff to handover, for example a website redesign starting Monday 16 November with three review rounds of three working days each, which moves launch from Friday 18 December to Thursday 31 December once the client’s review time is on the page.
Most timelines only show the work you do. The days a client spends reviewing are left out, so the plan looks shorter than it is and every late reply feels like your delay. This timeline maker puts review rounds and feedback windows on the chart as their own blocks, in a different colour, so both sides can see whose turn it is.
- Phase
- One block of the timeline with a name, a type and a length in working days. Phases run one after another in the order you list them.
- Working day
- Monday to Friday. Weekends are skipped, so a three-day review that starts on a Thursday ends on the following Monday. Public holidays are not skipped; add them as their own phase if they matter.
- Review round
- A block where the client looks at a version and sends one set of feedback. The timeline counts them, so the number on the chart can match the number in your contract.
- Client feedback window
- Time the client owes you something other than a review: content, logins, a licence or a decision. It is shown in the same colour as review rounds because the clock is on their side.
- Milestone
- A one-day marker such as “logo approved” or “final delivery”. Use it for the moments a payment or a sign-off is tied to.
- Client time
- All the working days in review rounds and feedback windows together. In the website example it is 9 of 34 working days, and it is the part you cannot speed up yourself.
An example project timeline, phase by phase
This is the website preset laid out by the same scheduler the tool uses. It is a fictional clinic site (example) starting on Monday 16 November 2026. Notice that weekends push each block forward and that the three review rounds add nine working days that a work-only plan would leave out.
| Phase (website example) | Type | Starts | Ends | Working days |
|---|---|---|---|---|
| Kickoff and content plan | Our work | Mon 16 Nov 2026 | Wed 18 Nov 2026 | 3 |
| Home page design | Our work | Thu 19 Nov 2026 | Wed 25 Nov 2026 | 5 |
| Design review, round 1 | Review round | Thu 26 Nov 2026 | Mon 30 Nov 2026 | 3 |
| Changes and inner pages | Our work | Tue 1 Dec 2026 | Mon 7 Dec 2026 | 5 |
| Design review, round 2 | Review round | Tue 8 Dec 2026 | Thu 10 Dec 2026 | 3 |
| Build | Our work | Fri 11 Dec 2026 | Thu 24 Dec 2026 | 10 |
| Staging review, round 3 | Review round | Fri 25 Dec 2026 | Tue 29 Dec 2026 | 3 |
| Fixes and launch | Our work | Wed 30 Dec 2026 | Thu 31 Dec 2026 | 2 |
Where a project timeline goes wrong
A timeline is a forecast, not a promise
Write in your proposal that dates move when feedback or content arrives after its window closes. Then a late reply moves the end date instead of squeezing your build time.
Holidays and time off are not on the chart
The tool skips weekends only. If the client’s office closes over the holidays or you are away for a week, add a phase called “Studio closed” so the dates stay honest.
Parallel work is drawn in sequence
Phases run one after another. If two things really happen at once, such as copywriting during design, list them as one phase with a clear name rather than two overlapping bars.
A short review window needs a named reviewer
Three days is only realistic if one person is responsible for collecting feedback. Name that person in the kickoff, or make the window longer.
Questions about the project timeline maker
Why does the project timeline maker show review rounds as separate blocks?
Because they take real calendar time and the client controls it. When reviews are hidden inside “design”, a slow reply looks like your delay. As separate blocks, everyone can see that week three is the client’s week.
Can I export the project timeline as an image?
Yes. Download a PNG to drop into a proposal or a slide, copy the plain text into an email, or print the sheet and save it as a PDF. Everything is drawn in your browser.
How many review rounds should a project timeline include?
As many as your contract says, and no more. Two or three is common for design work (example), but the right number is the one you priced. If the chart and the contract disagree, fix one of them before you send either.
What happens to the timeline if the client replies late?
Everything after that review moves by the same number of days. Change the length of that review block in the tool and the rest of the plan updates, which makes the new end date easy to explain.
Does the timeline maker skip public holidays?
No. It skips Saturdays and Sundays only, because holidays differ by country and by client. Add a short phase for any closure you know about.
Is a project timeline the same as a statement of work?
No. The statement of work says what is included and how sign-off works; the timeline shows when each part happens. Most proposals attach the timeline to the statement of work.